Recycling bulking facility photos

  • Site for RBF pre-construction July 2015
  • Piling work for foundations July 2015
  • Groundbeam and form work Oct 2015
  • Structural work Nov 2015
  • Steel erection Nov 2015
  • Roof sheeting Dec 2015
  • Cladding work to RBF building Jan 2016
  • Progression on external bays Feb 2016
  • RBF interior work March 2016
  • RBF in use April 2016
  • External bays in use April 2016
  • RBF Solar Panels complete and in use July 2016